2018-14 Betsy/N. Murphy Rd/McCreary Landscape and Irrigation Improvements

Overall Percent Complete

10%

2018-14Timeline

Status: Design progress at 90%; incorporating irrigation system design for bid issuance in March 2019.

50.42 Betsy/N. Murphy Rd/McCreary Landscape and Irrigation Improvements

Installation of irrigation within medians, retrofitting bed areas to drip irrigation, topsoil, landscape and sod.

Area Impacted:

50.42