2018-04 Right Turn Lane Northbound S Murphy Road @ F.M. 544

Progress

30%

2018-04TimeLine


April 10 - Survey data collection is substantially complete. Although complete with the collection of survey data this project may warrant the crews coming out to retrieve any missing information for design that is needed for the project. Conceptual design has begun.

50.12 Right Turn Lane Northbound S Murphy Road @ F.M. 544:

Installation of an additional right turn lane located on the southeast corner of South Murphy Road

Area Impacted:

2018-04